West Somerset Community College

Working for Somerset County Council Verde Recreo have constructed a new multi sports facility incorporating 2 MUGAS, a sand filled ATP, a polymeric sprint straight and 4 macadam tennis courts.


West Somerset Community College Image 1
West Somerset Community College Image 2
West Somerset Community College Image 3

Description

Verde Recreo were employed by Somerset County Council to construct a new sports facility for the use of West Somerset Community College and the wider community. The new facilities incorporate 2 acrylic coated macadam MUGAS designed primarily for football and basketball; a full size, multi use, sand filled artificial turf pitch with a polymeric trim trail surround; a polymeric sprint straight and long jumps and a block of 4 acylic coated macadam tennis courts.

All the facilities have a twinbar perimeter fence, with a 1.2m rebound panel included around the MUGAs and ATP. A floodlighting system was also installed allowing the facilities to be lit either individually or in combination.

 


Client

Somerset County Council
County Hall
Taunton
Somerset
TA1 4DY

Project Diary

Working on the MUGAS
fri 16 Jan 2009

Our first week on site. Despite inclement weather we have kerbed the MUGAS, imported the stone and trimmed using the laser dozer. The MUGAS are now ready for the porous macadam surfacing.

Importing the stone onto the ATP
fri 23 Jan 2009

We have begun working on the ATP, installing the drainage and importing the stone blanket.

Kerbing to the perimeter of the ATP
fri 30 Jan 2009

A busy week. We have installed the roots for the floodlighting system as well as all the cabling. The majority of the kerbs have been laid around the ATP, and the tarmacing has started on the MUGA

Floodlights to the ATP
fri 06 Feb 2009

We lost 2 days to the snow this week, but were still able to carry on with the kerbing to the ATP and put the luminaires on the floodlights

Tipping the sand into the long jump pits
fri 13 Feb 2009

The site has thawed out this week, and we have pushed ahead, getting the stone to the ATP and athletics track trimmed and ready for tarmacing. All the floodlights are up and wired and we took delivery of the sand for the long jump pits.

Starting the tarmac to the ATP
fri 20 Feb 2009

We've been laying the bitmac to the ATP and sprint straight this week, making the best of the good weather. The fencing materials were delivered to site and we began fencing the MUGA.

Spectator fence to the ATP
fri 27 Feb 2009

The bitmac to the ATP and sprint straight was completed and straight edged this week. We installed the spectator fence to the ATP in preparation for the shock pad to be laid next week.

fri 06 Mar 2009

We laid the shock pad to the ATP this week, along with the pad for the athletics facility. The fence to the MUGA is almost complete.

fri 13 Mar 2009

The weather has been kind to us this week. We had 2 days with low winds and so have been able to complete the spray coat to the athletics facility. We can now push on with the carpet laying next week.

Rolling out carpet
fri 20 Mar 2009

The carpet was delivered on Tuesday and we started rolling them out on Wednesday. The carpet team will be working over the weekend and will have the pitch green by Sunday.

Sanding up the carpet
fri 27 Mar 2009

The carpet team have been sanding up this week, and completed the infill this week. The fence to the ATP is progressing well.

Fencing the ATP
fri 03 Apr 2009

The sand infill to the artificial carpet has been completed this week, thanks to the dry weather. The fencing team have been pushing on with the ATP fence and are nearing completion.

Grading the clay loam
fri 10 Apr 2009

The natural pitches are taking shape. The topsoil has been spread and prepped for seeding. Work is ongoing on the cricket wicket with the clay loam being graded and compacted.

Hockey goal
fri 17 Apr 2009

The goal equipment for the ATP has been delivered and assembled this week, the hand over date is fast approaching.

Basketball Court
fri 24 Apr 2009

The acrylic spray coat to the MUGAs has been completed, which is the icing on the cake. The access works to the ATP and MUGA's is underway and we will be ready for handover next week.

Access footpath
fri 01 May 2009

The access works have been completed, the ATP given a final groom and the ATP and MUGA's have been handed over to the College. The works to the tennis courts will begin next week.

Installing the kerbs
fri 08 May 2009

We have imported the majority of the stone for the tennis courts and installed the perimeter kerbs.

© Copyright Verde Recreo 2010  |  Developed by Boson Media  | Site Map