Filton High School MUGA

Verde Recreo have commenced work at Filton High School. The school is being entirely re-built and we have been asked to provide a 77m x 37m porous macadam MUGA, for tennis, netball and basketball use.


Filton High School MUGA Image 1
Filton High School MUGA Image 2
Filton High School MUGA Image 3

Description

Bam construction, the main contractor at the Filton High School, have awarded Verde Recreo the contract to design and build a new macadam MUGA. This is Phase 1 of the contract, Phase 2 is a full sized sand filled ATP which will commence after the demolition of the old school.

The MUGA will be enclosed with a 3m high twinbar fence and will provide a block of 4 combined tennis / netball and basketball courts. The courts will be individually floodlit. Work commenced on the 7th December 2009


Client

Bam Construction
Millenium Gate
Fox Den Road
Bristol
BS34 8TT
www.hbgc.co.uk

Project Diary

In the soup
fri 11 Dec 2009

A wet and muddy field was the starting point. We scraped off the slop, filled in the low spots and had started the drainage by the end of the week.

Spreading the stone sub-base
fri 18 Dec 2009

A busy week. We completed the drainage and installed the infra structure for the floodlighting system. We were then able to complete the reduced dig to the formation and import the initial stone blanket, meaning the end of the mud. Happy Christmas.

Before the snows came!
fri 08 Jan 2010

We returned to site, completed the stone blanket and began preparing the kerb races. Then the snow came and covered the site with 4 inches, causing a temporary site closure.

A wintry scene
fri 15 Jan 2010

A near total white out this week. The snow finally melted on Friday, but it was still too cold to lay kerbs.

Kerbs to the pitch
fri 22 Jan 2010

Back on site at last. We laid the kerbs to the pitch perimeter and the laser dozer trimmed the stone blanket up, ready for surfacing.

Laying the macadam
fri 29 Jan 2010

The fencers started on site this week installing the posts. The tarmac gang followed straight after and commenced laying the binder course macadam.

Nearly there
fri 05 Feb 2010

The surface course macadam was completed this week, the consultant straight edged the court and it was all in tolerance. The fencers returned to site and completed the cladding to the fence.

The completed MUGA
fri 05 Mar 2010

After a long wait, the court was finally dry enough to add the finishing touch. The Line marking team attended site and marked out 4 sets of Tennis, Netball and Basketball courts. The lights were also commissioned this week and the MUGA is ready for handover.

© Copyright Verde Recreo 2010  |  Developed by Boson Media  | Site Map