Yatton Junior Football Club

Verde Recreo are installing a 40m x 40m, 3rd generation football training pitch, for Yatton Junior Football Club. The project includes a twinbar perimeter fence, floodlighting and upgrading works to the car park.


Yatton Junior Football Club Image 1
Yatton Junior Football Club Image 2
Yatton Junior Football Club Image 3

Description

Five years in the planning and financing, Verde Recreo have been chosen by Yatton Junior Football Club to create a 3G artificial turf pitch, suitable for football training and Futsal. The site originally housed a block of 2 macadam tennis courts. These will be planed up and used as a base for the new pitch. New drainage will be installed under the pitch, before kerbing and the importation of a stone sub-base. A dynamic layer of aggregate will be trimmed to a fine tolerance, upon which a Greenfields FT XP 50 will be installed.

A 3m high twinbar fence is specified to enclose the court, and 4, ten metre high floodlight columns will be illumination to 200 Lux. The project also requires the extending and re-surfacing of the existing car park.


Client

Yatton Junior Football Club
Rectory Way
Yatton
Bristol
BS49 4JF

Project Diary

Planing the old macadam tennis courts.
fri 12 Feb 2010

By the end of this week we had: set up the site, planed the tarmac, stripped the topsoil, installed the pitch drainage, installed the cable ducts, kerbed the pitch and imported the initial stone blanket.

Erecting the floodlights
fri 19 Feb 2010

The floodlights were erected and connected at the start of the week. The dynamic layer was imported and trimmed using the laser dozer.

A view across the car park extension
fri 26 Feb 2010

The new drainage system to the car park was installed this week. We laid a concrete edging to the perimeter and imported the stone sub-base for the car park extension.

The fence and a Church
fri 05 Mar 2010

We began the fence installation this week. We plan to get the new pitch secure before we start installing the carpet.

Green. green grass
fri 12 Mar 2010

The carpet was delivered to site on Tuesday. By Wednesday night it was rolled out and jointed. The sand infill layer was applied on Thursday and the rubber crumb infill was started on Friday

The 3G Pitch
fri 19 Mar 2010

We completed the rubber infill to the carpet and groomed it up. The perimeter fencing was also completed this week.

Car Parking in Yatton
fri 26 Mar 2010

The macadam to the car park and extension area was completed this week.

Fancy a kick about?
fri 02 Apr 2010

The site has been tidied, the security fence removed and the gates opened to Yatton Junior Football Club's new 3rd generation artificial training pitch.